Tuesday, May 1, 2012

Week 3.  This is a busy week!  We are making major progress on some electrical changes, and the groundwork, literally, is being laid!

Our driveway now has a lengthy mound of dirt... and all of our power/cable/etc cords are buried under it!

Not much different happening inside the old carport, but the siding on the eaves has been ripped off.  Not much more that can be removed at this point!

This was the mound of dirt/sand where the new bathroom will go, and now it is hard-packed dirt/sand.  I think it's ready for the slab to be poured.

The new electrical meter on the outside rear of the house.  It's ready to go!

The ditch leading from the end of the driveway around to the back of the house where the electrical meter is.  It's our own mini canyon!

The new interior panel box is up.  Well, maybe this isn't the whole box, but this is the spot for it, even though we don't have walls yet!  Big electrical changes are coming!

1 comment:

  1. Very impressive with the new electric box in place on the back wall and your canyon running down the driveway! Don't they need to put some plumbing connections in the new bathroom before pouring the slab? I do realize that I know less than nothing about construction!
    Love,
    Dad

    ReplyDelete